Now, AIMIX ALQ80 asphalt batch mixing plant is being installed in order at the construction site in Indonesia. Actually, the asphalt mixing plant has arrived at the port in the end of April, 2023. The client brought it to the construction site and requested to carry out installation as soon as possible. Thus, AIMIX engineers in Indonesia came to the site and started to install it immediately.
In general, it takes 40~60 days to install the batch type asphalt plant until it can normally working at the construction site, including installaing, testing, and debugging processes.
Because the asphalt mixing plant is a large road construction equipment, the installation process is relatively complex. Here is a general overview of the installation procedure:
It is necessary to construct a solid foundation to support the asphalt mixing plant’s weight and ensure stability.
Install the main components of the asphalt mixing plant in Indonesia, including the cold feed bins, conveyor systems, drying drum, hot aggregate storage bins, mixing unit, asphalt storage tanks, and control room.
Connect the electrical and plumbing systems, includding wiring the control panel, connecting motors, sensors, and instruments, etc.
Install air pollution control devices such as baghouses, dust collectors, or scrubbers; Ensure compliance with Indonesian local environmental regulations regarding emissions.
Set up the storage system for asphalt, which may include tanks or silos for storing the finished product.
Conduct comprehensive testing and calibration of the asphalt mixing plant’s components and systems and run trial batches to test the performance and quality of the asphalt produced by the equipment.
Provide training to the operators and maintenance personnel on the operation, maintenance, and safety procedures of the stationary asphalt mixing plant.
The installation of asphalt plant equipment including the above steps generally. Let’s look forward to finishing installation of AIMIX ALQ80 in Indonesia.